B22K (AEC-AON)
Station Notes
- ADOPTED BY AEC
- Station is built on a sand dune hummock, be prepared for sand abrasion on hut and the need to rebury the well cap cover.
Due to a drilling difficulty, the top of casing is essentially at ground level; the well cap box was tightly hammered on and siliconed in place to prevent leakage. However, the sand should be very well drained, so risk of flooding is minimal.
Service Plan
Site Access
- Helicopter from Barrow
- Fuel may be available in Umiat
Site Contact
- No site contact
Site Visits
- 2018_08_16 Service (R. Bierma, D. Bloomquist)
2017_08_11 Install (R. Bierma and M. Sanders)
Station Health
70.34002, -153.41963, Elev: 144ft
Permits
Landowner | Permit Expires | Notification | Stipulations |
---|---|---|---|
|
|
| |
| |||
AEC- Primary Permit Holder | NA | NA | Adopted by the AEC |