USArray Station Service Report
Form V1.0
STATION CODE:
TA.E25K
Station Local Description:
Arctic Village, AK, US
STATION SERVICE LOG DATE:
20181019
STATION SENSOR DOWN TIME (UTC):
Station has been down for several months due to power problem
SERVICE DESCRIPTION:
Install temporary alternate AC power system
UPON ARRIVAL:
Aside from having no power, the station is in good condition.
ACTION TAKEN
A 40 foot trench was chipped out of the frozen ground across the main road to the airport using a trencher and Hilti hammer drills. Minimum depth of the trench in some places was only 4-5", but we were able to cover the IMC conduit completely and were assured by the grader driver that he doesn't grade down to the surface during the winter.
300 feet of 10/3 UF direct-bury cable was strung out along the ground and through the conduit between the power garage and the F&W shack. A small LB was installed in the garage wall to pass cable through. The cable is terminated with a standard wall plug. We added a single GFCI device in line as a precaution in case of cable damage outside. We also have no guarantee that the plug won't be pulled at some point, but we chose the one that seemed least likely to be messed with. The other end of the cable was routed through our preexisting sub box that was never wired, it made for a neat pass through the wall and wired into our own dedicated circuit. AC power at our circuit in the F&W shack was 118.9V, so only a slight drop in the 300 feet distance.
All power systems were tested sequentially before devices were plugged in. Everything tested out well. Repowering the TA equipment was a simple unplug and replug into a different outlet.
EQUIPMENT REMOVED:
n/a
EQUIPMENT INSTALLED:
n/a
COMMENTS:
The trenching work was very difficult and uncooperative. We had hoped the ground hadn't frozen up quite so solid yet this early in the season The trencher that we flew in from Fairbanks, a 450 pound heavy duty machine, struggled mightily with the frozen ground. Much of the actual progress was made using Hilti hammer drills and chisel bits. In places we were able to get down about 10-12", but some places were only 4-5" depth. If were had another full day to dedicate to chipping away, we could get a proper 10-12" for the conduit, but the impending terrible weather, daylight, and pilot duty day were all closing us down.
PBO's AC station power connection was rewired off of their standard breaker circuit and onto an appliance plug; this in now plugged into the dedicated TA outlet. All PBO systems appeared to return to normal- the NetRS had correct lights and blinks, the comms came back online within a couple minutes of power up. The two batteries were swapped because they were down to 2.5V.
The station is fully operational again, however it must be emphasized that this is a temporary fix. We need to proactively address the power problem in Spring. We were assured by the grader driver that the conduit depth was good enough and both he and Jim H. said that draping the cable along the ground down to the garage would be fine. My biggest concerns are: a) a snow machine ski catching the cable and ripping it out, and b) once Spring comes and the road thaws that the grader will dig in too deep and catch the conduit. Jason and I both agreed that it would be a good idea to follow up on this several times this winter. Hopefully Jim will be willing to send reports back, but it may be worth having someone fly out to check at some point.
We should keep a close and consistent eye on the AC power/charging. This system has higher probability than normal for failure, whether through the plug being pulled in the garage or the cable being damaged. If any problems are noticed, Jim Hollandsworth should be contacted immediately, check the Wiki for his contact info.
VISITOR:
Ryan Bierma
Jason Theis
Matt (Everts pilot)
ON NEXT VISIT:
Properly fix the AC power system. This will require an electrician from Fairbanks and a lot of time and planning. It will not happen until after full thaw in the summer, 2019.
Several things need to be re-wired/properly wired in the building for the TA and PBO equipment once it looks like power will be fixed.